Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time-Cost Trade-Off Problem
Oluşturanlar
- 1. Middle E Tech Univ, Dept Civil Engn, TR-06531 Ankara, Turkey
- 2. Minist Dev, Necatibey Caddesi 110-A, TR-06570 Ankara, Turkey
Açıklama
Despite the importance of project deadlines and resource constraints in construction scheduling, very little success has been achieved in solving the resource-constrained discrete time-cost trade-off problem (RCDTCTP), especially for large-scale projects. In this paper a new heuristic method is designed and developed to achieve fast and high-quality solutions for the large-scale RCDTCTP. The proposed method is based on the novel principles to enable effective exploration of the search space through adequate selection of the activities to be crashed for a resource constrained schedule, by only crashing the activities with zero float in a resource constrained-schedule, which form the critical sequence. The computational experiment results reveal that the new critical sequence crashing heuristic outperforms the state-of-the-art methods, both in terms of the solution quality concerning project cost and computation time. Solutions with a deviation of 0.25% from the best known solutions are achieved within seconds for the first time, for a large-scale project including up to 2,000 activities. The main contribution of the new heuristic to practitioners and researchers is that it provides a fast and effective method for optimal scheduling of real-life-size construction projects with project deadlines and resource constraints. (C) 2015 American Society of Civil Engineers.
Dosyalar
bib-725fd633-5c91-457e-8121-b13de9c5a03b.txt
Dosyalar
(203 Bytes)
| Ad | Boyut | Hepisini indir |
|---|---|---|
|
md5:582ba5e9a4813b784c9fa43d166e69dd
|
203 Bytes | Ön İzleme İndir |